JOHOR 2022 P1 Q10
MediumWrite your answer on paper. Then open the answer to check it.
A contractor digs an oil well. The cost to dig the first 2 m is RM600, the second 2 m is RM680 and the third 2 m is RM760. The cost increases by a constant amount for every subsequent 2 m. Find (a) the cost to dig the 12th 2 m, (b) the cost to dig a 120 m deep oil well, (c) the depth of the oil well if the company's budget is half a million (RM500 000).
Medium8 marks- (a)
Find the cost to dig the 12th 2 m.
[2] - (b)
Find the cost to dig a 120 m deep oil well.
[2] - (c)
Find the depth of the oil well if the budget is RM500 000.
[4]